Project Brief, The Collab Lab

Smart Shopping List

Locations for things

  • Site: {PRODUCTION_URL}
  • Repo: {REPO_URL}
  • Clone URL: {REPO_CLONE_URL}
  • Issue list: {PROJECT_BOARD_URL}
  • Database: {CONSOLE_URL}

Project cadence & duration

The project is expected to take 40 hours per participant, spread over 8 weeks.

Each week, the team of 4 developers will split into 2 pairs of 2 developers each. Each pair will take on a story or task from the issues list to work on together that week.

Pairings will go as follows:

Week 1, {DATES_WEEK_1}

  1. {DEV_1} & {DEV_2}
  2. {DEV_3} & {DEV_4}

Week 2, {DATES_WEEK_2}

  1. {DEV_2} & {DEV_3}
  2. {DEV_1} & {DEV_4}

Week 3, {DATES_WEEK_3}

  1. {DEV_3} & {DEV_1}
  2. {DEV_4} & {DEV_2}

Week 4, {DATES_WEEK_4}

  1. {DEV_1} & {DEV_2}
  2. {DEV_3} & {DEV_4}

Week 5, {DATES_WEEK_5}

  1. {DEV_2} & {DEV_3}
  2. {DEV_1} & {DEV_4}

Week 6, {DATES_WEEK_6}

  1. {DEV_3} & {DEV_1}
  2. {DEV_4} & {DEV_2}

Week 7, {DATES_WEEK_7}

  1. {DEV_1} & {DEV_2}
  2. {DEV_3} & {DEV_4}

Week 8, {DATES_WEEK_8}

  1. {DEV_2} & {DEV_3}
  2. {DEV_1} & {DEV_4}