Skip to content
New issue

Have a question about this project? Sign up for a free GitHub account to open an issue and contact its maintainers and the community.

By clicking “Sign up for GitHub”, you agree to our terms of service and privacy statement. We’ll occasionally send you account related emails.

Already on GitHub? Sign in to your account

Task requiring more resources #129

Open
davideschiavone opened this issue Aug 22, 2023 · 0 comments
Open

Task requiring more resources #129

davideschiavone opened this issue Aug 22, 2023 · 0 comments

Comments

@davideschiavone
Copy link

Dear all,

thanks a lot for the work you have done! amazing!

Quick question, I am trying the Resource constrained project scheduling example, and I would like to know whether you will provide a way to solve a problem where one job requires more resources than the one provided.

For example, the JOB1 requires 5 C1 resources over a total of 6 C1 resources.

If it requires 8 resources, the program fails - but it could solve this by first satisfying the first 6, then the last 2 (time multiplexing).

This can be done by defining a new job "1B" that depends on the job "1A" where I separate by hand the 2 jobs - but this fails in having the whole picture view (i.e. other jobs scheduled and mapped in parallel) as maybe it would be better to do first 3 C1 jobs and then the remaining 5 (because in parallel some other job are also needing C1).

Let me know your thoughts,

thanks
Davide